Case study · Power & HV

Feeder station upgrade programme.

Design and install works to upgrade protection and control on feeder stations supporting mainline AC electrification. Energised without service disruption.

GBP 8m
Value band
18 months
Duration
Delivered
Status
Summary

Scope, route and status at a glance.

Client
Tier-one alliance
Capability
Power & HV
Region
North
Value band
GBP 8m
Duration
18 months
Status
Delivered
The challenge

Delivered inside constrained possession windows, without disrupting passenger service.

Scope required design completion, installation and full commissioning within a series of weekend and overnight possessions. Daytime services continued uninterrupted.

What we delivered

End-to-end power & hv scope, self-delivered.

Detailed design, installation, isolation and possession management, testing and commissioning, handback and entry-into-service packs.

Outcome

On programme. Zero unplanned disruption.

Scope delivered on programme. Zero unplanned service disruption attributable to RC Infrastructure works. Entry-into-service packs cleared audit on first submission.

On programme · In possession

Delivered. Audited. Handed back ready for service.

Every scheme in our case study pack was self-delivered inside possession. Entry-into-service packs cleared audit on first submission. References and full project documentation available on PQQ or tender request.